CUP: F37H17001890001
LAVORI PER LA RIQUALIFICAZIONE FUNZIONALE DELLA SEGNALETICA VERTICALE, MARGINALE ED ORIZZONTALE IN TRATTI SALTUARI LUNGO LA SS 514 DAL KM 0+000 AL KM 41+000
SUMMARY OF THE PROJECT
RIPRISTINO DELLA SEGNALETICA VERTICALE ESISTENTE ED INTEGRAZIONE DELLA STESSA NEL RISPETTO DEL CODICE DELLA STRADA VIGENTE
Implementation indicators
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 41 km
- Achieved
- 20 km
Lunghezza totale delle strade ricostruite o rinnovate di cui: TEN-T
- Target
- 41 km
- Achieved
- 20 km
km di strade ristrutturate (core indicator n° 16)
- Target
- 41 km
- Achieved
- 20 km
- Slide 1
- Slide 2
- Slide 3
Funding monitored
€ 1,471,875.00
of which cohesion funds
€ 1,471,875.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1471875.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: 05/01/2018
Effective start: 23/01/2018
Expected end: 08/11/2018
Effective end: 04/10/2018
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- ANAS SOCIETA PER AZIONI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PATTO SICILIA
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture di trasporto ferroviario e stradale