CUP: J11H92000000008
COMPLETAMENTO DEL G.P. RADDOPPIO FERROVIARIO PALERMO CENTRALE Â CARINI TRATTA URBANA A
SUMMARY OF THE PROJECT
COMPLETAMENTO DEL G.P. RADDOPPIO FERROVIARIO PALERMO CENTRALE Â CARINI TRATTA URBANA A - PROGETTO IN FASE CON IL PO FESR 2007/2013
Public cost
€ 41,278,849.00
Given name | Amount |
---|---|
Another public source | 41278849.00 |
Payments
€ 22,872,254.26
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 9327700.03 | 9327700.03 | 22 |
2017 | 3145041.77 | 12472741.80 | 30 |
2018 | 6333462.40 | 18806204.20 | 45 |
2019 | 4066050.06 | 22872254.26 | 55 |
State of progress
Open
Expected start: 22/02/2008
Effective start: 22/02/2008
Expected end: 31/12/2019
Effective end: not available
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- RFI SPA
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- POR FESR SICILIA
- Axis
- Sistemi di Trasporto Sostenibili
- Specific objective
- POTENZIAMENTO DELL'OFFERTA FERROVIARIA E MIGLIORAMENTO DEL SERVIZIO IN TERMINI DI QUALITÃ E TEMPI DI PERCORRENZA
Other projects in territory
Same theme
Same type of investment
SISTEMA TRAM CITTA' DI PALERMO | € 304,548,123 |
RADDOPPIO FERROVIARIO PALERMO - CARINI - TRATTA B - NOTABARTOLO - EMS/LA MALFA | € 290,894,000 |
SISTEMA TRAM PALERMO - FASE II | € 198,872,027 |
COMPLETAMENTO COLLETTORE FOGNARIO DELLA ZONA SUD-EST DI PALERMO. (33414) | € 47,313,795 |
SCMT SOTTOSISTEMA TERRA SICILIA | € 47,194,288 |