CUP: J67B16000120001
RINNOVAMENTO CON CONTEMPORANEO RISANAMENTO DELLA MASSICCIATA DI BINARI DI CIRCOLAZIONE E SCAMBI NELLA TRATTA SCICLI  ROSOLINI DELLA LINEA SIRACUSA  CANICATTì  CALTANISSETTA, NONCHé MODIFICHE IS, TLC, CTC E SSC
SUMMARY OF THE PROJECT
RINNOVAMENTO CON CONTEMPORANEO RISANAMENTO DELLA MASSICCIATA DI BINARI DI CIRCOLAZIONE E SCAMBI NELLA TRATTA SCICLI  ROSOLINI DELLA LINEA SIRACUSA  CANICATTì  CALTANISSETTA, NONCHé MODIFICHE IS, TLC, CTC E SSC
Implementation indicator
Estensione dell'intervento in lunghezza
- Target
- 37,400 M
- Achieved
- 37,400 M
Public cost
€ 25,010,000.00
Given name | Amount |
---|---|
Another public source | 25010000.00 |
Payments
€ 20,450,371.74
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2017 | 9206836.40 | 9206836.40 | 36 |
2018 | 9774224.71 | 18981061.11 | 75 |
2019 | 1469310.63 | 20450371.74 | 81 |
State of progress
Open
Expected start: 26/10/2016
Effective start: 26/10/2016
Expected end: 28/02/2020
Effective end: 02/03/2020
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- RFI SPA
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- POR FESR SICILIA
- Axis
- Sistemi di Trasporto Sostenibili
- Specific objective
- POTENZIAMENTO FERROVIARIO REGIONALE, INTEGRAZIONE MODALE E MIGLIORAMENTO DEI COLLEGAMENTI MULTIMODALI CON I PRINCIPALI NODI URBANI, PRODUTTIVI E LOGISTICI E LA RETE CENTRALE, GLOBALE E LOCALE