CUP: J93J07000020006
NISCEMI - INTEGRAZIONE DELLA CAPACITÃÂ DI RISERVA ATTUALMENTE DISPONIBILE. CL-042
Funding monitored
€ 1,501,251.59
of which cohesion funds
€ 1,641,800.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1501251.59 |
- Economies:
- € 140,548.41
Payments monitored
€ 1,501,229.11
of which cohesion funds
€ 1,501,229.11
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2010 | 148877.84 | 148877.84 | 9 |
2011 | 760707.33 | 909585.17 | 60 |
2012 | 309390.94 | 1218976.11 | 81 |
2013 | 0 | 1218976.11 | 81 |
2014 | 186993.00 | 1405969.11 | 93 |
2015 | 95260.00 | 1501229.11 | 99 |
State of progress
Completed
Expected start: 08/01/2008
Effective start: 11/07/2008
Expected end: 01/01/2010
Effective end: 31/10/2012
Type
- Infrastructure
- NUOVA REALIZZAZIONE
Theme
- Environment
- Gestione e distribuzione d'acqua (potabile)
Territory
Entities
- Planning body
- REGIONE SICILIANA
- Implementing body
- AMBITO TERRITORIALE OTTIMALE DI CALTANISSETTA
- Beneficiary
- AMBITO TERRITORIALE OTTIMALE DI CALTANISSETTA
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
- Specific objective QSN
- Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- ROP CONV ERDF SICILY
- Axis
- Uso efficiente delle risorse naturali
- Operational objective
- Realizzare int.infrastrutt.prioritari lungo le fasi del ciclo delle acque,realizz.le infrastrutt.previste nella pianif.reg.le vigente,da assoc.al risp.idrico,riduz.di perdite,uso di fonti idriche alternat.,implem.strum.di pianificaz.sett.le.