CUP: J67J19000030001

LINEA FERROVIARIA PALERMO-TRAPANI VIA CASTELVETRANO - TRATTA ALCAMO DIRAMAZIONE-CASTELVETRANO-MARSALA-TRAPANI UPGRADING DELL'ARMAMENTO E MIGLIORAMENTO DELLA SICUREZZA DELL'INFRASTRUTTURA FERROVIARIA

SUMMARY OF THE PROJECT

LINEA FERROVIARIA PALERMO ¿ TRAPANI VIA CASTELVETRANO ¿ TRATTA ALCAMO DIRAMAZIONE - CASTELVETRANO ¿ MARSALA ¿ TRAPANI ¿UPGRADING DELL'ARMAMENTO E MIGLIORAMENTO DELLA SICUREZZA DELL'INFRASTRUTTURA FERROVIARIA

Implementation indicator

Estensione dell'intervento in lunghezza

Target
74,000 M
Achieved
39,500 M
Updated on 30/04/2020
Public cost € 54,500,000.00
Given name Amount
European Union43600000.00
Another public source10900000.00
Payments € 16,787,805.58
Year Amount Cumulative amount Percentage on public financing
201916787805.5816787805.5830

State of progress

Open
Expected start: 06/05/2019
Effective start: 01/05/2019
Expected end: 12/09/2021
Effective end: not available

Type

Theme

Territory

Entities

Planning body
REGIONE SICILIANA
Beneficiary
RFI SPA - RETE FERROVIARIA ITALIANA

Programming area

European Regional Development Fund (ERDF)
2014-2020 EU Structural Funds
Programme
POR FESR SICILIA
Axis
Sistemi di Trasporto Sostenibili
Specific objective
POTENZIAMENTO FERROVIARIO REGIONALE, INTEGRAZIONE MODALE E MIGLIORAMENTO DEI COLLEGAMENTI MULTIMODALI CON I PRINCIPALI NODI URBANI, PRODUTTIVI E LOGISTICI E LA RETE CENTRALE, GLOBALE E LOCALE