CUP: J64J17000010001
LINEA FERROVIARIA CANICATTì-GELA-RAGUSA-SIRACUSA UPGRADE TECNOLOGICO E INFRASTRUTTURALE
SUMMARY OF THE PROJECT
LINEA FERROVIARIA CANICATTì GELA RAGUSA SIRACUSA - UPGRADE TECNOLOGICO ED INFRASTRUTTURALE
Implementation indicator
Estensione dell'intervento in lunghezza
- Target
- 24,254 M
- Achieved
- 24,234 M
Funding monitored
€ 11,900,000.00
of which cohesion funds
€ 11,900,000.00
Given name | Amount |
---|---|
European Union | 9520000.00 |
Another public source | 2380000.00 |
Payments monitored
€ 10,798,650.08
of which cohesion funds
€ 10,798,650.08
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 10798650.08 | 10798650.08 | 90 |
State of progress
Open
Expected start: 06/12/2017
Effective start: 08/12/2017
Expected end: 04/08/2020
Effective end: not available
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- RETE FERROVIARIA ITALIANA SOCIETA' PER AZIONI - RFI S.P.A.
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- POR FESR SICILIA
- Axis
- Sistemi di Trasporto Sostenibili
- Specific objective
- POTENZIAMENTO FERROVIARIO REGIONALE, INTEGRAZIONE MODALE E MIGLIORAMENTO DEI COLLEGAMENTI MULTIMODALI CON I PRINCIPALI NODI URBANI, PRODUTTIVI E LOGISTICI E LA RETE CENTRALE, GLOBALE E LOCALE