CUP: I43J13000030007
REALIZZAZIONE NUOVO IMPIANTO DI DEPURAZIONE IN TORTORETO LIDO A SERVIZIO DI TORTORETO E GIULIANOVA NORD - SECONDO LOTTO
SUMMARY OF THE PROJECT
REALIZZAZIONE NUOVO IMPIANTO DI DEPURAZIONE IN TORTORETO LIDO A SERVIZIO DI TORTORETO E GIULIANOVA NORD - SECONDO LOTTO
This project is no longer active and is therefore excluded from totals and search results
Funding monitored
€ 3,300,000.00
of which cohesion funds
€ 0.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 3300000.00 |
Payments monitored
€ 329,267.11
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 329267.11 | 329267.11 | 9 |
State of progress
Open
Expected start: 15/11/2018
Effective start: 27/11/2018
Expected end: 27/10/2019
Effective end: not available
Entities
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PATTO ABRUZZO
- DCF strategic sector
- Ambiente
- DCF area axis
- Servizio idrico integrato