CUP: I92B17000060001

DIGA BAU PRESSIU 1A.S1 PROTEZIONE CONDOTTA IN ACCIAIO CIXERRI -POTABILIZZATORE. REALIZZAZIONE STRADA DI ACCESSO AL CORONAMENTO

SUMMARY OF THE PROJECT

MESSA IN SICUREZZA DELLA CONDOTTA IN ACCIAIO CIXERRI-POTABILIZZATORE DI BAU PRESSIU DAGLI SMOTTAMENTI PROVENIENTI DALLA SCARPATA DELLA SS N 293. REALIZZAZIONE STRADA DI ACCESSO AL CORONAMENTO.

Implementation indicator

Numero di azioni/progetti finanziati

Target
1
Achieved
0
Updated on 31/03/2019
Public cost € 1,500,000.00
Given name Amount
Development and Cohesion Fund1500000.00
Payments € 0.00
Year Amount Cumulative amount Percentage on public financing

State of progress

Not started
Expected start: 01/01/2022
Effective start: not available
Expected end: 31/12/2022
Effective end: not available

Type

Theme

Territory

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
PATTO PER LO SVILUPPO REGIONE SARDEGNA
DCF strategic sector
Ambiente
DCF area axis
Servizio idrico integrato