CUP: I47H17000110002
VIABILITA' COMUNALE - COMUNE DI SAN GIOVANNI SUERGIU
SUMMARY OF THE PROJECT
INTERVENTI DI MANUTENZIONE E MESSA IN SICUREZZA DELLE STRADE URBANE
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 KM
- Achieved
- 1 KM
Public cost
€ 90,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 90000.00 |
Payments
€ 88,147.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 88147.00 | 88147.00 | 97 |
State of progress
Completed
Expected start: 24/04/2018
Effective start: 04/06/2018
Expected end: 10/07/2018
Effective end: 25/06/2018
Entities
- Planning body
- REGIONE AUTONOMA DELLA SARDEGNA
- Implementing body
- COMUNE DI SAN GIOVANNI SUERGIU
- Beneficiary
- COMUNE DI SAN GIOVANNI SUERGIU
- Executor
-
UFFICIO PER LA TRANSIZIONE AL DIGITALE
TROGU MASSIMILIANO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PATTO SARDEGNA
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture di trasporto ferroviario e stradale
Other projects in territory
Same theme
Same implementing bodies
Same type of investment
086 COMUNE DI SAN GIOVANNI SUERGIU-- ISTITUTO COMPRENSIVO--CA000126-- | € 312,275 |
SAN GIOVANNI SUERGIU - COMPLETAMENTO CAMPI DA TENNIS CENTRO, CALCETTO FRAZ. PALMAS E CAMPO SPORTIVO COMUNALE | € 286,279 |