CUP: J29J17000370002

VIABILITA' PROVINCIALE PROVINCIA SUD SARDEGNA

SUMMARY OF THE PROJECT

MANUTENZIONE STRAORDINARIA SUL PATRIMONIO VIARIO DELL ENTE INTERVENTI PRIORITARI DI MESSA IN SICUREZZA DELLA PIATTAFORMA STRADALE ED ADEGUAMENTO FUNZIONALE MANUFATTI CONNESSI

Implementation indicator

Lunghezza totale delle strade ricostruite o rinnovate

Target
1 KM
Achieved
0 KM
Updated on 31/03/2019
Public cost € 6,250,000.00
Given name Amount
Development and Cohesion Fund6250000.00
Payments € 0.00
Year Amount Cumulative amount Percentage on public financing

State of progress

Not started
Expected start: 23/08/2019
Effective start: not available
Expected end: 21/09/2020
Effective end: not available

Entities

Planning body
REGIONE AUTONOMA DELLA SARDEGNA
Implementing body
PROVINCIA SUD SARDEGNA
Beneficiario
PROVINCIA SUD SARDEGNA

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
PATTO PER LO SVILUPPO REGIONE SARDEGNA
DCF strategic sector
Infrastrutture
DCF area axis
Infrastrutture di trasporto ferroviario e stradale

Other projects in territory