CUP: C37H17001310002

VIABILITA COMUNALE ED INTERCOMUNALE UNIONE DI COMUNI ALTA MARMILLA

SUMMARY OF THE PROJECT

MANUTENZIONE STRAORDINARIA RETE VIARIA

Implementation indicator

Lunghezza totale delle strade ricostruite o rinnovate

Target
5 KM
Achieved
0 KM
Updated on 31/05/2019
Public cost € 510,000.00
Given name Amount
Revolving Fund240000.00
Development and Cohesion Fund240000.00
Municipality30000.00
Payments € 0.00
Year Amount Cumulative amount Percentage on public financing

State of progress

Open
Expected start: 15/02/2019
Effective start: 18/03/2019
Expected end: 18/10/2019
Effective end: not available

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
PATTO SARDEGNA
DCF strategic sector
Infrastrutture
DCF area axis
Trasporto sostenibile urbano