CUP: G65D11000140002

ORDINANZA N. 5/2012 DEL COMMISSARIO DELEGATO- “GRUPPO N. 2.6 – RIPRISTINO DELLA OFFICIOSITà IDRAULICA E INTERVENTI SUGLI ARGINI DEL FIUME OFANTO – COMUNI DI MELFI (PZ) – CANDELA (FG)”

Updated on 30/04/2018
Public cost € 700,000.00
Given name Amount
European Union348798.03
Revolving Fund (National co-financing)279038.42
Revolving Fund (Cohesion Action Plan)2403.94
Region69759.61
Payments € 700,000.00
Year Amount Cumulative amount Percentage on public financing
2012105000.00105000.0015
2013100000.00205000.0029
2014495000.00700000.00100

State of progress

Completed
Expected start: 01/01/2007
Effective start: 01/01/2007
Expected end: 01/01/2007
Effective end: 01/01/2007

Type

Theme

  • Environment
  • Altre misure per tutelare l'ambiente e prevenire i rischi

Territory

Entities

Planning body
REGIONE BASILICATA
Implementing body
REGIONE BASILICATA
Beneficiario
REGIONE BASILICATA
Priority QSN
Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
General objective QSN
Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
Specific objective QSN
Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali

Programming area

European Regional Development Fund (ERDF)
2007-2013 EU Structural Funds
Programme
ROP CONV ERDF BASILICATA
Axis
Energia e sviluppo sostenibile
Operational objective
Salvaguardia e tutela del territorio attraverso interventi puntuali e diffusi finalizzati al raggiungimento o ripristino delle condizioni di sicurezza del territorio.
2007-2013 Cohesion Action Plan
2007-2013 Cohesion Action Plan
Programme
PROGRAMMA PAC BASILICATA
Line
Salvaguardia
Action
Prevenzione rischio ambientale