CUP: J55C12001130008
(0261000002B) THABOR MODULI INVERTER A SEMICONDUTTORE CON INNOVATIVA TECNOLOGIA DI INTERCONNESSIONE AD ALTA AFFIDABILITÃ E CON ADOZIONE DI UNA NUOVA GENERAZIONE DI DIODI DI POTENZA AD ALTA EFFICIENZA
SUMMARY OF THE PROJECT
(0261000002B) THABOR MODULI INVERTER A SEMICONDUTTORE CON INNOVATIVA TECNOLOGIA DI INTERCONNESSIONE AD ALTA AFFIDABILITÃ E CON ADOZIONE DI UNA NUOVA GENERAZIONE DI DIODI DI POTENZA AD ALTA EFFICIENZA
Implementation indicator
Giornate uomo prestate
- Target
- 1,800 num
- Achieved
- 1,800 num
Funding monitored
€ 963,873.66
of which cohesion funds
€ 204,425.87
Given name | Amount |
---|---|
Development and Cohesion Fund | 204425.87 |
Another public source | 759447.79 |
- Economies:
- € 59,126.34
Payments monitored
€ 963,873.66
of which cohesion funds
€ 204,425.87
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 824526.02 | 824526.02 | 85 |
2015 | 108483.27 | 933009.29 | 96 |
2016 | 0 | 933009.29 | 96 |
2017 | 0 | 933009.29 | 96 |
2018 | 0 | 933009.29 | 96 |
2019 | 0 | 933009.29 | 96 |
2020 | 30864.37 | 963873.66 | 100 |
State of progress
Completed
Expected start: 30/11/2010
Effective start: 07/01/2013
Expected end: 31/12/2015
Effective end: 31/12/2015
Entities
- Planning body
- A19000 DIREZIONE COMPETITIVITA' DEL SISTEMA REGIONALE
- Implementing body
- POLITECNICO DI TORINO
- Beneficiary
- POLITECNICO DI TORINO
- Executor
- POLITECNICO DI TORINO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC PIEDMONT
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Industria e servizi