CUP: I36B13000010006

(REG_2014_10.01 - ASP) RAZIONALIZZAZIONE DELLA RETE FOGNARIA DI ASTI

Updated on 28/02/2019
Public cost € 1,798,672.37
Given name Amount
Development and Cohesion Fund999336.19
Another public source799336.18
Economies:
€ 0.31
Payments € 1,577,359.78
Year Amount Cumulative amount Percentage on public financing
201581120.0081120.004
2016937482.261018602.2656
2017536045.631554647.8986
201822711.891577359.7887

State of progress

Open
Expected start: 25/11/2015
Effective start: 25/11/2015
Expected end: 27/10/2017
Effective end: 27/10/2017

Type

Theme

  • Environment
  • Altre misure per tutelare l'ambiente e prevenire i rischi

Territory

Entities

Planning body
REGIONE PIEMONTE
Implementing body
ASTI SERVIZI PUBBLICI S.P.A. (ASP S.P.A.)
Beneficiario
ASTI SERVIZI PUBBLICI S.P.A. (ASP S.P.A.)
Realizzatore
ASTI SERVIZI PUBBLICI S.P.A. (ASP S.P.A.)
Priority QSN
Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
General objective QSN
Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
Specific objective QSN
Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali

Programming area

2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Programme
PAR FSC PIEMONTE
Line
Sistema fluviale del PO e reti idriche
Action
Interventi sul servizio Idrico Integrato e per la tutela delle risorse idriche