CUP: F82I19000360001

LAVORI DI EFFICIENTAMENTO ENERGETICO E MESSA IN SICUREZZA DI PARTE DELL'IMPIANTO DI PUBBLICA ILLUMINAZIONE CITTADINO - OPERE COMPLEMENTARI

SUMMARY OF THE PROJECT

IL PROGETTO PREVEDE L¿ INTERVENTO DI COMPLETAMENTO DELLA VIA SARDEGNA, LA RIQUALIFICAZIONE DELL¿ IMPIANTO DI ILLUMINAZIONE NELLA VIA ROMA E NELLA VIA ANGIOY, UN INTERVENTO NELLA PIAZZA PUBBLICA DELLA BIBLIOTECA.

Implementation indicator

Punti illuminanti/luce

Target
20
Achieved
20
Updated on 31/03/2021
Funding monitored € 29,702.67 of which cohesion funds € 29,702.67
Given name Amount
Development and Cohesion Fund29702.67
Economies:
€ 1,297.33
Payments monitored € 29,702.67 of which cohesion funds € 29,702.67
Year Amount Cumulative amount Percentage on public financing
202029393.7929393.7998
2021308.8829702.67100

State of progress

Completed
Expected start: 23/12/2019
Effective start: 23/12/2019
Expected end: 22/03/2020
Effective end: 11/05/2020

Type

  • Infrastructure
  • MANUTENZIONE STRAORDINARIA CON EFFICIENTAMENTO ENERGETICO

Theme

Territory

Entities

Planning body
COMUNE DI MACOMER
Beneficiary
COMUNE DI MACOMER

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
EFFICIENTAMENTO ENERGETICO NEI COMUNI
DCF strategic sector
Interventi di efficientamento energetico e sviluppo territoriale sostenibile
DCF area axis
Interventi di efficientamento energetico e sviluppo territoriale sostenibile