CUP: E82I19000040005

INTERVENTI DI EFFICIENTAMENTO ENERGETICO PRESSO EPICERIE E BIBLIOTECA COMUNALI

SUMMARY OF THE PROJECT

BIBLIOTECA: SOSTITUZIONE DI GENERATORE DI CALORE ESISTENTE CON POMPA DI CALORE ARIA-ACQUA A CICLO INVERTIBILE ABBINATA AD UN NUOVO IMPIANTO FOTOVOLTAICO; EPICERIE: INSTALLAZIONE DI POMPA DI CALORE

Implementation indicator

Diminuzione del consumo annuale di energia primaria degli edifici pubblici

Target
24,946 KWH/A
Achieved
-
Updated on 30/04/2020
Public cost € 71,587.22
Given name Amount
Development and Cohesion Fund50000.00
Municipality21587.22
Payments € 0.00
Year Amount Cumulative amount Percentage on public financing

State of progress

Open
Expected start: 29/10/2019
Effective start: 29/10/2019
Expected end: 29/05/2020
Effective end: not available

Type

  • Infrastructure
  • MANUTENZIONE STRAORDINARIA CON EFFICIENTAMENTO ENERGETICO

Theme

Territory

Entities

Planning body
COMUNE DI SAINT-DENIS
Beneficiary
COMUNE DI SAINT-DENIS

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
EFFICIENTAMENTO ENERGETICO NEI COMUNI
DCF strategic sector
Interventi di efficientamento energetico e sviluppo territoriale sostenibile
DCF area axis
Interventi di efficientamento energetico e sviluppo territoriale sostenibile