OPERA DI RIPRISTINO OPERA DI PRESA E TUBATURA ACQUEDOTTO LUNGO IL RIO CASTELIR
SUMMARY OF THE PROJECT
INTERVENTO DI VIABILITÃ AL FINE DI RIPRISTINARE IL COLLEGAMENTO CON L'OPERA DI PRESA DELLA CENTRALINA IDROELETTRICA DEL SENTIERO CASTELIR BASA, PER RIATTIVARNE L'OPERATIVITÃ
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 0.70 km
- Achieved
- 1 km
Funding monitored
€ 53,485.43
of which cohesion funds
€ 17,080.72
Given name | Amount |
---|---|
Development and Cohesion Fund | 17080.72 |
Municipality | 36404.71 |
- Economies:
- € 2,014.57
Payments monitored
€ 53,485.43
of which cohesion funds
€ 17,080.72
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 8590.89 | 8590.89 | 16 |
2020 | 44894.54 | 53485.43 | 100 |
State of progress
Completed
Expected start: 10/05/2019
Effective start: 13/05/2019
Expected end: 03/11/2019
Effective end: 02/11/2019
Entities
- Planning body
- COMUNE DI ZIANO DI FIEMME
- Beneficiary
- COMUNE DI ZIANO DI FIEMME
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
INSTALLAZIONE IMPIANTO FOTOVOLTAICO - SCUOLA ELEMENTARE (14 - IMPIANTI FOTOVOLTAICI IN RETE) | € 265,535 |
I - COGENERAZIONE | € 145,888 |
IMPIANTO FOTOVOLTAICO | € 98,871 |
A - RETI ENERGETICHE | € 94,539 |
DIAGNOSI ENERGETICA DI OTTO IMMOBILI PUBBLICI | € 18,876 |