CUP: F51B13000280002

PORTO DI GIOIA TAURO: COMPLETAMENTO VIABILITà COMPARTO NORD

SUMMARY OF THE PROJECT

LA FINALITà DELL¿INTERVENTO Ê CONSENTIRE LA CIRCOLAZIONE VEICOLARE ALL'INTERNO DELL'AREA PORTUALE CON MARGINI DI SICUREZZA ADEGUATI, EVITANDO DI UTILIZZARE LE BANCHINE COME ARTERIE DI TRANSITO E ADEGUANDO LE INFRASTRUTTURE ESISTENTI ALLE NUOVE NORMATIVE EUROPEE

Updated on 30/06/2022
Funding monitored € 18,176,833.00 of which cohesion funds € 18,176,833.00
Given name Amount
European Union13632624.75
Revolving Fund4544208.25
Payments monitored € 10,976,295.44 of which cohesion funds € 10,976,295.44
Year Amount Cumulative amount Percentage on public financing
20163852006.003852006.0021
20174461611.288313617.2845
20182290204.1610603821.4458
2019272458.0010876279.4459
2020100016.0010976295.4460

State of progress

Open
Expected start: 15/10/2015
Effective start: 16/10/2015
Expected end: 20/11/2019
Effective end: 23/07/2019

Type

Theme

Territory

Programming area

European Regional Development Fund (ERDF)
2014-2020 EU Structural Funds
Programme
PON FESR INFRASTRUTTURE E RETI
Axis
SVILUPPARE E MIGLIORARE SISTEMI DI TRASPORTO SOSTENIBILI DAL
Specific objective
Miglioramento della competitività del sistema portuale e interportuale (Cfr. R.A. 7.2)