CUP: J96B07000030005

COMPLETAMENTO DELL'AEROPORTO INTER. DELL'UMBRIA "SAN FRANCESCO D'ASSISI" PG

Updated on 31/12/2018
Public cost € 42,618,226.35
Given name Amount
Development and Cohesion Fund8000000.00
Status: other measures26808226.35
Region4500000.00
Another public source3310000.00
Payments € 38,420,980.15
Year Amount Cumulative amount Percentage on public financing
20093948986.153948986.159
20108572239.0012521225.1529
201116827148.0029348373.1568
20129072607.0038420980.1590

State of progress

Open
Expected start: 27/05/2009
Effective start: 27/05/2009
Expected end: 18/06/2012
Effective end: 27/07/2012

Type

Theme

Territory

Entities

Planning body
REGIONE UMBRIA
Implementing body
PRESIDENZA DEL CONSIGLIO DEI MINISTRI- UNITA TECNICA DI MISSIONE
Beneficiario
PRESIDENZA DEL CONSIGLIO DEI MINISTRI- UNITA TECNICA DI MISSIONE
Realizzatore
CONSORZIO STABILE CENTRITALIA S.C.P.A.
Priority QSN
Reti e collegamenti per la mobilità
General objective QSN
Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
Specific objective QSN
Contribuire alla realizzazione di un sistema logistico nazionale, supportando la costruzione di una rete nazionale di terminali di trasporto e di logistica, integrata, sicura, interconnessa ed omogenea

Programming area

2007-2013 National Development and Cohesion Fund
2007-2013 National Development and Cohesion Fund
Programme
PAR FSC UMBRIA
Line
Realizzazione dell'aeroporto regionale
Action
Realizzazione dell'aeroporto regionale

Other projects in territory