CUP: F47H21000780001

"SS 417 - SS117BIS" LAVORI DI COMPLETAMENTO DELLA MANUTENZIONE PROGRAMMATA DAL KM 0+000 AL KM 12+000 DELLA SS 417 IN T.S. E DAL KM 73+240 AL KM 91830 DELLA SS117BIS"

SUMMARY OF THE PROJECT

INTERVENTI DI MANUTENZIONE STRAORDINARIA DI TIPO PUNTUALE E DIFFUSO VOLTI ALLA RISOLUZIONE DI NODI CRITICI. GLI INTERVENTI COMPRENDERANNO INTERVENTI DI: LAVORI PER LA REALIZZAZIONE DELLE OPERE IDRAULICHE A DIFESA DEL CORPO STRADALE TRA IL KM 0+000 ED IL KM 12+000 DELLA S.S.N°417 IN T.S; REALIZZAZIONE DELLE OPERE IDRAULICHE E DELLE OPERE DI SOSTEGNO A DIFESA DEL CORPO STRADALE TRA IL KM 0+000 ED IL KM 12+000 IN T.S. DELLA S.S. N° 417; REALIZZAZIONE DELLE OPERE IDRAULICHE A DIFESA DEL CORPO STRADALE TRA IL KM 73+240 ED IL KM 91+830 IN T.S. DELLA S.S. N° 117/ BIS; LAVORI PER LA REALIZZAZIONE DELLE OPERE IDRAULICHE E DELLE OPERE DI SOSTEGNO, A DIFESA DEL CORPO STRADALE TRA IL KM 73+240 ED IL KM 91+830 IN T.S. DELLA S.S. N° 117/ BIS; LAVORI DI RIQUALIFICAZIONE FUNZIONALE DELLE BARRIERE DI SICUREZZA TRA IL KM 0+000 ED IL KM 12+000 IN T.S. DELLA S.S. N° 417; LAVORI DI RIQUALIFICAZIONE FUNZIONALE DELLE BARRIERE DI SICUREZZA TRA IL KM 73+240 ED IL KM 91+830 IN T.S. DELLA S.S. N° 117/ BIS;

Implementation indicator

Lunghezza totale delle strade ricostruite o rinnovate

Target
12 KM
Achieved
0 KM
Updated on 28/02/2022
Funding monitored € 11,865,656.25 of which cohesion funds € 11,865,656.25
Given name Amount
Development and Cohesion Fund11865656.25
Payments monitored € 0.00 of which cohesion funds € 0.00
Year Amount Cumulative amount Percentage on public financing

State of progress

Open
Expected start: 11/10/2022
Effective start: not available
Expected end: 13/11/2023
Effective end: not available

Type

Theme

Territory

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
PIANO FSC INFRASTRUTTURE
DCF strategic sector
Infrastrutture
DCF area axis
Infrastrutture di trasporto ferroviario e stradale