CUP: I71B19000640001
LAVORI DI COMPLETAMENTO FUNZIONALE DELL'ARTERIA IN DIREZIONE VALLE CAUDINA - S.S. N. 7 APPIA - IV LOTTO EX VI LOTTO - COMPLETAMENTO
SUMMARY OF THE PROJECT
LAVORI DI COMPLETAMENTO FUNZIONALE DELL'ARTERIA IN DIREZIONE VALLE CAUDINA - S.S. N. 7 APPIA - IV LOTTO EX VI LOTTO - COMPLETAMENTO
Implementation indicator
Lunghezza totale delle strade di nuova costruzione
- Target
- 2.50 km
- Achieved
- 0 km
Funding monitored
€ 9,300,000.00
of which cohesion funds
€ 9,300,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 9300000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 01/06/2023
Effective start: not available
Expected end: 02/09/2024
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI BENEVENTO
- Beneficiary
- REGIONE CAMPANIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale