CUP: H51B20000150002

2_¿ STRADA PROVINCIALE DEL CARPINELLO¿ COMPLETAMENTO

SUMMARY OF THE PROJECT

2_¿ STRADA PROVINCIALE DEL CARPINELLO¿ COMPLETAMENTO

Implementation indicator

Lunghezza totale delle strade di nuova costruzione

Target
2.28 KM
Achieved
0 KM
Updated on 31/10/2021
Funding monitored € 5,400,000.00 of which cohesion funds € 5,400,000.00
Given name Amount
Development and Cohesion Fund5400000.00
Payments monitored € 18,683.64 of which cohesion funds € 0.00
Year Amount Cumulative amount Percentage on public financing
202018683.6418683.640

State of progress

Open
Expected start: 31/01/2022
Effective start: not available
Expected end: 30/06/2023
Effective end: not available

Type

Theme

Territory

Entities

Planning body
MIT-DGSTRADE
Implementing body
PROVINCIA DI MATERA
Beneficiary
REGIONE BASILICATA - UFFICIO INFRASTRUTTURE

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
PIANO FSC INFRASTRUTTURE
DCF strategic sector
Infrastrutture
DCF area axis
Infrastrutture di trasporto ferroviario e stradale