CUP: E11B07000380001

TANGENZIALE SUD DI FORMIGINE (MO)

SUMMARY OF THE PROJECT

REALIZZAZIONE COLLEGAMENTO AREA PRODUTTIVA SUD DI FORMIGINE CON S.S. 724 MODENA - DIRAMAZIONE FIORANO MODENESE/SASSUOLO

Implementation indicator

Lunghezza totale delle strade di nuova costruzione

Target
1.30 KM
Achieved
0 KM
Updated on 31/12/2018
Public cost € 5,415,000.00
Given name Amount
Development and Cohesion Fund5415000.00
Payments € 0.00
Year Amount Cumulative amount Percentage on public financing

State of progress

Open
Expected start: 31/01/2019
Effective start: not available
Expected end: 31/01/2020
Effective end: not available

Type

Theme

Territory

Entities

Planning body
MIT-DGSTRADE
Implementing body
FORMIGINE PATRIMONIO SRL
Beneficiario
COMUNE DI FORMIGINE

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
PIANO OPERATIVO FSC INFRASTRUTTURE
DCF strategic sector
Infrastrutture
DCF area axis
Infrastrutture di trasporto ferroviario e stradale

Other projects in territory

Same theme

8 - LINEA FERROVIARIA MODENA-SASSUOLO € 5,706,605