CUP: F87H16002740003

RISANAMENTO ED ALSFALTATURA STRADE DI ACCESSO AI MASI "TABLANDERHÖFE" (NATURNO)

SUMMARY OF THE PROJECT

ESECUZIONE DI PROVVEDIMENTI IMMEDIATI E LAVORI DI MANUTENZIONE ECCEZIONALI SISTEMAZIONE E ASFALTURA DELLA STRADA D'ACCESSO PER I MASI DI TABLÀ

Implementation indicator

Lunghezza totale delle strade ricostruite o rinnovate

Target
4 KM
Achieved
4 KM
Updated on 28/02/2022
Funding monitored € 440,460.00 of which cohesion funds € 440,460.00
Given name Amount
Development and Cohesion Fund440460.00
Payments monitored € 440,460.00 of which cohesion funds € 440,460.00
Year Amount Cumulative amount Percentage on public financing
2020122000.00122000.0027
2021318460.00440460.00100

State of progress

Completed
Expected start: 17/12/2019
Effective start: 17/12/2019
Expected end: 31/10/2021
Effective end: 30/09/2021

Type

Theme

Territory

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
PIANO FSC INFRASTRUTTURE
DCF strategic sector
Infrastrutture
DCF area axis
Infrastrutture di trasporto ferroviario e stradale