CUP: F81B16000640001

SS.N. 87 SANNITICA-LAVORI DI AMMODERNAMENTO DELLA SS 87. INTERVENTI LOCALIZZATI PER GARANTIRE LA PERCORRIBILITà IMMEDIATA DEL TRATTO CAMPOBASSO - BIVIO S. ELIA - LOTTI A1, A2 E A3 (STRALCIO)

SUMMARY OF THE PROJECT

L¿INTERVENTO, CHE SI PONE IN CONTINUITà CON GLI INTERVENTI ESEGUITI, PREVEDE IL MIGLIORAMENTO DEGLI STANDARD ESISTENTI LUNGO LA S.S. 87. TRATTASI INFATTI DI ADEGUAMENTO DEL TRACCIATO STRADALE ALLA SEZIONE TIPO C2 DELLE NORME GEOMETRICHE DM 2001. CON I FINANZIAMENTI DISPONIBILI SARà SVILUPPATO UNO STRALCIO RELATIVO AI SOLI LOTTI A2 E A3.

Implementation indicator

Lunghezza totale delle strade ricostruite o rinnovate

Target
3.40 KM
Achieved
0 KM
Updated on 30/06/2022
Funding monitored € 12,000,000.00 of which cohesion funds € 12,000,000.00
Given name Amount
Development and Cohesion Fund12000000.00
Payments monitored € 0.00 of which cohesion funds € 0.00
Year Amount Cumulative amount Percentage on public financing

State of progress

Open
Expected start: 01/01/2022
Effective start: not available
Expected end: 31/12/2023
Effective end: not available

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
PIANO FSC INFRASTRUTTURE
DCF strategic sector
Infrastrutture
DCF area axis
Altre infrastrutture