CUP: G13E18000030001

INTERVENTI DI MESSA IN SICUREZZA DEL POZZO DI ACCESSO ALLA CAMERA DI MANOVRA DELLE PARATOIE E DI RIPRISTINO DELLA CORRETTA FUNZIONALITÀ DELL¿INVASO -DIGA TIMPA DI PANTALEO

SUMMARY OF THE PROJECT

MANUTENZIONE STRAORDINARIA E MESSA IN SICUREZZA DEL POZZO DI MANOVRA DELLO SCARICO DI FONDO, CONSOLIDAMENTO DEL VERSANTE SUL QUALE Ê POSTO IL POZZO, INTEGRAZIONE DELLA STRUMENTAZIONE DI CONTROLLO.

Implementation indicator

Popolazione beneficiaria di misure di protezione contro le alluvioni

Target
20,000
Achieved
0
Updated on 31/10/2020
Public cost € 9,720,000.00
Given name Amount
Development and Cohesion Fund9720000.00
Payments € 0.00
Year Amount Cumulative amount Percentage on public financing

State of progress

Not started
Expected start: 10/10/2021
Effective start: not available
Expected end: 15/12/2023
Effective end: not available

Type

Theme

Territory

Entities

Planning body
MIT-DGDIGHE
Beneficiary
CONSORZIO DI BONIFICA ALTO JONIO REGGINO

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
PIANO FSC INFRASTRUTTURE
DCF strategic sector
Infrastrutture
DCF area axis
Altre infrastrutture