CUP: B89H18000250002
DIGA CROSTOLO Â STRUMENTAZIONE CONTROLLO INDAGINI GEOT.STRUT. E MIGLIORAMENTO DELLA SICUREZZA STRUTTURALE E IDRAULICA DELLA TRAVERSA
SUMMARY OF THE PROJECT
à NECESSARIO INTERVENIRE CON LE SEGUENTI ATTIVITà : 1. ESECUZIONE DI RILIEVI E DI INDAGINI GEOTECNICHE E STRUTTURALI; 2. ESECUZIONE DI VERIFICHE IDROLOGICHE, IDRAULICHE E SISMICHE NONCHé DEGLI STUDI DELLE ONDE DI PIENA PER MANOVRA DEGLI ORGANI DI SCARICO E PER IPOTETICO COLLASSO DELLO SBARRAMENTO; 3. ADEGUAMENTI IMPIANTISTICI URGENTI: REALIZZAZIONE DELL¿IMPIANTO DI ILLUMINAZIONE, RIPRISTINO DEL GRUPPO ELETTROGENO, RIPRISTINO DELL¿ACCESSIBILITà DEL CUNICOLO E DELLA FUNZIONALITà DELLE CANNE DI DRENAGGIO COMPRESA LA MESSA IN OPERA DI STRUMENTI DI MISURA PER LA VERIFICA DELLE PERDITE ALL¿INTERNO DEL CUNICOLO; 4. ADEGUAMENTO STRUTTURALE E IMPIANTISTICO DEL MANUFATTO.
Implementation indicator
Popolazione beneficiaria di misure di protezione contro le alluvioni
- Target
- 104,563.08 num
- Achieved
- 0 num
Funding monitored
€ 6,350,000.00
of which cohesion funds
€ 6,350,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 6350000.00 |
Payments monitored
€ 716,800.10
of which cohesion funds
€ 716,800.10
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 38064.00 | 38064.00 | 0 |
2020 | 161137.60 | 199201.60 | 3 |
2021 | 326174.94 | 525376.54 | 8 |
2022 | 191423.56 | 716800.10 | 11 |
State of progress
Open
Expected start: 13/07/2023
Effective start: not available
Expected end: 12/07/2024
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- AGENZIA INTERREGIONALE PER IL FIUME PO AIPO
- Beneficiary
- AGENZIA INTERREGIONALE PER IL FIUME PO AIPO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche
Other projects in territory
Same theme
LAVORI NEL TRATTO DEL TORRENTE CROSTOLO E TORRENTE MODOLENA NEI COMUNI DI VEZZANO QUATTRO CASTELLA E REGGIO EMILIA | € 170,000 |