CUP: B51F18000350001

CICLOVIA ADRIATICA: PONTE CICLOPEDONALE SUL FIUME CHIENTI

SUMMARY OF THE PROJECT

REALIZZAZIONE PONTE CICLOPEDONALE ALLA FOCE DEL FIUME CHIENTI

Implementation indicator

Beneficiari/Popolazione Beneficiaria

Target
3,440.75
Achieved
0
Updated on 30/06/2022
Funding monitored € 2,000,000.00 of which cohesion funds € 2,000,000.00
Given name Amount
Development and Cohesion Fund2000000.00
Payments monitored € 41,378.02 of which cohesion funds € 41,378.02
Year Amount Cumulative amount Percentage on public financing
202016921.5316921.530
202124456.4941378.022

State of progress

Open
Expected start: 01/01/2023
Effective start: not available
Expected end: 01/07/2023
Effective end: not available

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
PIANO FSC INFRASTRUTTURE
DCF strategic sector
Infrastrutture
DCF area axis