CUP: D58I16000030008
SVILUPPO DI PIATTAFORMA TECNOLOGICA INTEGRATA PER IL CONTROLLO E LA TRASMISSIONE INFORMATICA DI DATI SUI CAMPI PRECIPITATIVI IN TEMPO REALE
SUMMARY OF THE PROJECT
SVILUPPO DI PIATTAFORMA TECNOLOGICA INTEGRATA PER IL CONTROLLO E LA TRASMISSIONE INFORMATICA DI DATI SUI CAMPI PRECIPITATIVI IN TEMPO REALE
Implementation indicator
Giornate uomo prestate
- Target
- 4,440.88 num
- Achieved
- 1,656 num
Funding monitored
€ 831,881.26
of which cohesion funds
€ 474,230.03
Given name | Amount |
---|---|
Development and Cohesion Fund | 474230.03 |
Region | 357651.23 |
- Other resources - Private:
- € 514,161
Payments monitored
€ 831,881.26
of which cohesion funds
€ 474,230.03
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 160120.00 | 160120.00 | 19 |
2017 | 21280.00 | 181400.00 | 21 |
2018 | 281566.70 | 462966.70 | 55 |
2019 | 0 | 462966.70 | 55 |
2020 | 368914.56 | 831881.26 | 100 |
State of progress
Completed
Expected start: 01/07/2015
Effective start: 09/09/2016
Expected end: 11/03/2019
Effective end: 11/03/2019
Entities
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE TOSCANA
- Policy Area
- Ricerca e Innovazione
- Sector of intervention
- Ricerca e Sviluppo