CUP: B46J99000650003
GRANDE PROGETTO ' COMPLETAMENTO DELLA LINEA 6 DELLA METROPOLITANA DI NAPOLI - TRATTA MERGELLINA (STAZIONE ESCLUSA)/ SAN PASQUALE/ MUNICIPIO (STAZIONE INCLUSA)'
SUMMARY OF THE PROJECT
GRANDE PROGETTO ' COMPLETAMENTO DELLA LINEA 6 DELLA METROPOLITANA DI NAPOLI - TRATTA MERGELLINA (STAZIONE ESCLUSA)/ SAN PASQUALE/ MUNICIPIO (STAZIONE INCLUSA)'. BENEFICIARIO: COMUNE DI NAPOLI
Implementation indicator
Estensione dell'intervento in lunghezza
- Target
- 6,300 M
- Achieved
- 0 M
Funding monitored
€ 200,142,412.47
of which cohesion funds
€ 200,142,412.47
Given name | Amount |
---|---|
European Union | 150106809.35 |
Revolving Fund | 35024922.18 |
Region | 15010680.94 |
Payments monitored
€ 176,239,417.98
of which cohesion funds
€ 176,239,417.98
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 2994891.15 | 2994891.15 | 1 |
2015 | 10090786.63 | 13085677.78 | 6 |
2016 | 33808357.53 | 46894035.31 | 23 |
2017 | 16817417.44 | 63711452.75 | 31 |
2018 | 75579268.38 | 139290721.13 | 69 |
2019 | 20918374.58 | 160209095.71 | 80 |
2020 | 15316356.23 | 175525451.94 | 87 |
2021 | 713966.04 | 176239417.98 | 88 |
State of progress
Open
Expected start: 31/05/2017
Effective start: not available
Expected end: 31/01/2022
Effective end: not available
Entities
- Planning body
- REGIONE CAMPANIA
- Beneficiary
- COMUNE DI NAPOLI
- Executor
- ANSALDO STS SPA
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- POR FESR CAMPANIA
- Axis
- ENERGIA SOSTENIBILE
- Specific objective
- AUMENTO DELLA MOBILITÃ SOSTENIBILE NELLE AREE URBANE