ISTITUTO AUTONOMO CASE POPOLARI

Go to list of projects
Data in euro
Updated on 30/04/2020, 2017-13 UE Programmes data under review and 2014-20 UE Programmes progressive loading

Territories

Where does funding go?

Given name Value
PUGLIA 2526766

Roles

What role does he play in the projects?

Given name Value
Beneficiary / Implementing body 2526765.59
Data in euro
Updated on 30/04/2020, 2017-13 UE Programmes data under review and 2014-20 UE Programmes progressive loading

Territories

Where does funding go?

Given name Value
PUGLIA 1107465

Roles

What role does he play in the projects?

Given name Value
Beneficiary / Implementing body 1107464.83
Data in number of projects
Updated on 30/04/2020, 2017-13 UE Programmes data under review and 2014-20 UE Programmes progressive loading

Territories

Where does funding go?

Given name Value
PUGLIA 3

Roles

What role does he play in the projects?

Given name Value
Beneficiary / Implementing body 3

The entities with whom he works the most

REGIONE PUGLIA 3 projects

Developments in total commitments and payments

What has been allocated and paid over the years?

Year Commitments Payments
2015 914317.69 50379.73
2016 2526765.59 239088.67
2017 2526765.59 315594.09
2018 2526765.59 787893.98
2019 2526765.59 1107464.83

Projects completed most recently

Municipalities with most per-capita funding

Comune di Monteparano € 379
Comune di San Marzano di San Giuseppe € 126
Comune di Torricella € 105

The entirety of project funding is associated with the municipality, even when a project is located in multiple municipalities. Population numbers are as at 31/12/2011 (source: ISTAT).