Implementing bodies with most funding

COMUNE DI STENICO € 177,858
COMUNE DI S. LORENZO IN BANALE € 167,213
AZIENDA CONSORZIALE TERME DI COMANO ACTC € 148,878

Developments in total commitments and payments

What has been allocated and paid over the years?

Year Commitments Payments
2007 38025.04 11945.54
2008 65502.60 44328.55
2009 312126.28 91727.02
2010 353512.27 190204.94
2011 398788.24 344366.31
2012 417799.47 376171.30
2013 469834.25 423928.33
2014 467546.67 451936.23
2015 464400.61 464400.61