CUP: F61B04000370003
COMPLETAMENTO DELLA SORA ' FROSINONE 5A LOTTO, 1A STRALCIO FUNZIONALE'
SUMMARY OF THE PROJECT
COMPLETAMENTO DELLA SORA ' FROSINONE 5A LOTTO, 1A STRALCIO FUNZIONALE'
Implementation indicator
Estensione in lunghezza
- Target
- 5.50 km
- Achieved
- 5.50 km
Download project
Funding monitored
€ 78,374,930.56
of which cohesion funds
€ 28,021,630.12
Given name | Amount |
---|---|
Development and Cohesion Fund | 28021630.12 |
Region | 50353300.44 |
Payments monitored
€ 78,374,930.52
of which cohesion funds
€ 28,021,630.12
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2005 | 3848311.18 | 3848311.18 | 4 |
2006 | 4521740.03 | 8370051.21 | 10 |
2007 | 7479829.54 | 15849880.75 | 20 |
2008 | 7981139.12 | 23831019.87 | 30 |
2009 | 13109385.20 | 36940405.07 | 47 |
2010 | 11701268.40 | 48641673.47 | 62 |
2011 | 4973683.15 | 53615356.62 | 68 |
2012 | 0 | 53615356.62 | 68 |
2013 | 0 | 53615356.62 | 68 |
2014 | 190517.37 | 53805873.99 | 68 |
2015 | 17188247.63 | 70994121.62 | 90 |
2016 | 0 | 70994121.62 | 90 |
2017 | 0 | 70994121.62 | 90 |
2018 | 7380808.90 | 78374930.52 | 99 |
State of progress
Completed
Expected start: 31/08/2004
Effective start: 31/08/2004
Expected end: 02/08/2011
Effective end: 02/08/2011
Entities
- Planning body
- REGIONE LAZIO
- Implementing body
- SOPRINTENDENZA ARCHEOLOGICA PER L'ABRUZZO
- Beneficiary
- REGIONE LAZIO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC LAZIO
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale