CUP: F83B13000070001
IMPIANTO GEOTERMICO SCUOLA MATERNA VIA ALFORTVILLE
Funding monitored
€ 113,397.21
of which cohesion funds
€ 87,432.81
Given name | Amount |
---|---|
European Union | 31683.03 |
Revolving Fund (National co-financing) | 38294.40 |
Region | 11063.88 |
Municipality | 32355.90 |
- Economies:
- € 18,220.48
Payments monitored
€ 113,397.21
of which cohesion funds
€ 87,432.81
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 113397.21 | 113397.21 | 100 |
State of progress
Completed
Expected start: 02/12/2013
Effective start: 02/12/2013
Expected end: 07/03/2014
Effective end: 07/03/2014
Type
- Infrastructure
- AMPLIAMENTO O POTENZIAMENTO
Theme
- Energy
- Energia rinnovabile: idroelettrica, geotermale e altra
Territory
Entities
- Planning body
- REGIONE MARCHE
- Implementing body
- COMUNE DI SAN BENEDETTO DEL TRONTO
- Beneficiary
- COMUNE DI SAN BENEDETTO DEL TRONTO
- Executor
-
ELETTRO STELLA DI LUCIANI ENNIO & C. SNC
AREA ENGINEERING SRL
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Diversificazione delle fonti energetiche e aumento dell'energia prodotta da fonti rinnovabili
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- ROP RCE ERDF MARCHE
- Axis
- Efficienza energetica e promozione delle energie rinnovabili
- Operational objective
- Incrementare la produzione di energia da fonti rinnovabili.