CUP: B17H14001870007
RISANAMENTO ED ASFALTATURA STRADA D'ACCESSO AI MASI KRONLECHNER, ANGERLE E LAHNER - VARIAZIONE PONTE
SUMMARY OF THE PROJECT
RISANAMENTO ED ASFALTATURA STRADA D'ACCESSO AI MASI KRONLECHNER, ANGERLE E LAHNER - VARIAZIONE PONTE
Implementation indicator
Estensione in lunghezza
- Target
- 0.14 km
- Achieved
- 0.14 km
Funding monitored
€ 79,488.00
of which cohesion funds
€ 79,488.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 79488.00 |
- Other resources - Private:
- € 19,872
Payments monitored
€ 79,488.00
of which cohesion funds
€ 79,488.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 79488.00 | 79488.00 | 100 |
State of progress
Completed
Expected start: 20/05/2015
Effective start: 20/05/2015
Expected end: 13/05/2016
Effective end: 13/05/2016
Entities
- Planning body
- PROVINCIA AUTONOMA DI BOLZANO
- Implementing body
- INTERESSENZA HINTERTAL
- Beneficiary
- PROVINCIA AUTONOMA DI BOLZANO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC P.A. BOLZANO
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale
Other projects in territory
Same theme
ASFALTATURA STRADA DI ACCESSO AI MASI KRONLECHNER, ANGERLE E LAHNER | € 183,200 |
ASFALTATURA DELLA VIA BELLAVISTA - II LOTTO | € 112,000 |