CUP: B97B17000720002
CONSOLIDAMENTO AREE IN DISSESTO DEL CENTRO STORICO II LOTTO III STRALCIO FUNZIONALE
SUMMARY OF THE PROJECT
CONSOLIDAMENTO AREE IN DISSESTO DEL CENTRO STORICO II LOTTO III STRALCIO FUNZIONALE
Implementation indicator
Progetti per la fruizione integrata e la promozione
- Target
- 1 num
- Achieved
- 0 num
Funding monitored
€ 1,500,000.00
of which cohesion funds
€ 1,500,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1500000.00 |
Payments monitored
€ 225,000.00
of which cohesion funds
€ 225,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 61999.91 | 61999.91 | 4 |
2020 | 0 | 61999.91 | 4 |
2021 | 0 | 61999.91 | 4 |
2022 | 2192.00 | 64191.91 | 4 |
2023 | 160808.09 | 225000.00 | 15 |
State of progress
Open
Expected start: 15/01/2023
Effective start: 29/11/2022
Expected end: 15/01/2024
Effective end: not available
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- COMUNE DI BOMBA
- Beneficiary
- COMUNE DI BOMBA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE ABRUZZO
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico