CUP: F54H15000400002
RISTRUTTURAZIONE CAMPO SPORTIVO
SUMMARY OF THE PROJECT
RISTRUTTURAZIONE CAMPO SPORTIVO
Implementation indicator
Superficie oggetto di intervento
- Target
- 1,296 mq
- Achieved
- 1,296 mq
Download project
Funding monitored
€ 93,521.99
of which cohesion funds
€ 93,521.99
Given name | Amount |
---|---|
Development and Cohesion Fund | 93521.99 |
- Economies:
- € 978.01
Payments monitored
€ 93,521.99
of which cohesion funds
€ 93,521.99
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 1030.00 | 1030.00 | 1 |
2017 | 92394.39 | 93424.39 | 99 |
2018 | 97.60 | 93521.99 | 100 |
State of progress
Completed
Expected start: 10/05/2016
Effective start: 10/05/2016
Expected end: 04/08/2016
Effective end: 28/02/2017
Entities
- Planning body
- REGIONE ABRUZZO
- Implementing body
- COMUNE DI MAGLIANO DE MARSI
- Beneficiary
- REGIONE ABRUZZO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE ABRUZZO
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e Paesaggio