CUP: H17H13000130001
S.P. EX SS 103 (TRATTO BIVIO STIGLIANO-CIRIGLIANO E BIVIO FONDOVALLE FIUMARA). OPERE DI CONSOLIDAMENTO.
SUMMARY OF THE PROJECT
S.P. EX SS 103 (TRATTO BIVIO STIGLIANO-CIRIGLIANO E BIVIO FONDOVALLE FIUMARA). OPERE DI CONSOLIDAMENTO.
Implementation indicator
Estensione in lunghezza
- Target
- 8.50 km
- Achieved
- 8.50 km
Funding monitored
€ 171,337.45
of which cohesion funds
€ 171,337.45
Given name | Amount |
---|---|
Development and Cohesion Fund | 171337.45 |
Payments monitored
€ 171,337.45
of which cohesion funds
€ 171,337.45
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2016 | 169243.04 | 169243.04 | 98 |
2017 | 0 | 169243.04 | 98 |
2018 | 836.13 | 170079.17 | 99 |
2019 | 1258.28 | 171337.45 | 100 |
State of progress
Completed
Expected start: 29/03/2016
Effective start: 19/04/2016
Expected end: 16/10/2016
Effective end: 16/10/2016
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- REGIONE BASILICATA
- Beneficiary
- REGIONE BASILICATA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE BASILICATA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale