CUP: D58H20000450001
IMPIANTO SPORTIVO*MOLINO SAN NICOLA*RIGENERAZIONE E COMPLETAMENTO
SUMMARY OF THE PROJECT
IMPIANTO SPORTIVO*MOLINO SAN NICOLA*RIGENERAZIONE E COMPLETAMENTO
Funding monitored
€ 699,737.71
of which cohesion funds
€ 699,737.71
Given name | Amount |
---|---|
Development and Cohesion Fund | 699737.71 |
Payments monitored
€ 346,704.47
of which cohesion funds
€ 346,704.47
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 30500.00 | 30500.00 | 4 |
2023 | 316204.47 | 346704.47 | 49 |
State of progress
Open
Expected start: 03/04/2023
Effective start: not available
Expected end: 09/08/2023
Effective end: not available
Entities
- Planning body
- PRESIDENZA DEL CONSIGLIO DEI MINISTRI
- Implementing body
- COMUNE DI BELLANTE
- Beneficiary
- COMUNE DI BELLANTE
- Executor
- CEAR - SOCIETA' COOPERATIVA CONSORTILE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC PRESIDENZA CONSIGLIO MINISTRI DIPARTIMENTO SPORT
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici