CUP: H37H20001560001
LAVORI DI MANUTENZIONE STRAORDINARIA DELLA PAVIMENTAZIONE BITUMINOSA DELLA S.P.5 (TRATTO CRACO PESCHIERA - S.S. N. 598 - INCROCO S.S. 653 SINNICA)
SUMMARY OF THE PROJECT
LAVORI DI MANUTENZIONE STRAORDINARIA DELLA PAVIMENTAZIONE BITUMINOSA DELLA S.P.5 (TRATTO CRACO PESCHIERA - S.S. N. 598 - INCROCO S.S. 653 SINNICA)
Implementation indicator
Estensione in lunghezza
- Target
- 8.50 km
- Achieved
- 8.50 km
Funding monitored
€ 117,080.70
of which cohesion funds
€ 117,080.70
Given name | Amount |
---|---|
Development and Cohesion Fund | 117080.70 |
- Economies:
- € 7.58
Payments monitored
€ 117,080.70
of which cohesion funds
€ 117,080.70
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 29426.00 | 29426.00 | 25 |
2021 | 87654.70 | 117080.70 | 100 |
State of progress
Completed
Expected start: 28/09/2020
Effective start: 28/09/2020
Expected end: 28/10/2020
Effective end: 07/10/2020
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI MATERA
- Beneficiary
- AMMINISTRAZIONE PROVINCIALE DI MATERA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE BASILICATA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale