CUP: F89G08000120001
COMPLETAMENTO LAVORI DI CONSOLIDAMENTO E RESTAURO CHIESA S. MARIA DEL POGGIO (COMUNE DI RIVELLO - PZ)
SUMMARY OF THE PROJECT
COMPLETAMENTO LAVORI DI CONSOLIDAMENTO E RESTAURO CHIESA S. MARIA DEL POGGIO (COMUNE DI RIVELLO - PZ)
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Funding monitored
€ 842,208.45
of which cohesion funds
€ 842,208.45
Given name | Amount |
---|---|
Development and Cohesion Fund | 842208.45 |
Payments monitored
€ 842,208.45
of which cohesion funds
€ 842,208.45
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2009 | 10649.90 | 10649.90 | 1 |
2010 | 441.54 | 11091.44 | 1 |
2011 | 267.88 | 11359.32 | 1 |
2012 | 0 | 11359.32 | 1 |
2013 | 102541.41 | 113900.73 | 13 |
2014 | 1337.66 | 115238.39 | 13 |
2015 | 108981.77 | 224220.16 | 26 |
2016 | 0 | 224220.16 | 26 |
2017 | 617988.29 | 842208.45 | 100 |
State of progress
Completed
Expected start: 20/03/2013
Effective start: 20/03/2013
Expected end: 14/06/2016
Effective end: 14/06/2016
Entities
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE BASILICATA
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e paesaggio