CUP: I48F04000020009
AMMODERNAMENTO, AMPLIAMENTO E RAZIONALIZZAZIONE DELLA RETE FOGNANTE DELL'IMPIANTO DI DEPURAZIONE E REALIZZAZIONE CONDOTTA RACCOLTA ACQUE BIANCHE SUL TERRITORIO COMUNALE
SUMMARY OF THE PROJECT
AMMODERNAMENTO, AMPLIAMENTO E RAZIONALIZZAZIONE DELLA RETE FOGNANTE DELL'IMPIANTO DI DEPURAZIONE E REALIZZAZIONE CONDOTTA RACCOLTA ACQUE BIANCHE SUL TERRITORIO COMUNALE
Implementation indicator
Capacita' trattamento reflui oggetto di intervento
- Target
- 0.01 mc/s
- Achieved
- 0.01 mc/s
Funding monitored
€ 5,285,305.06
of which cohesion funds
€ 5,285,305.06
Given name | Amount |
---|---|
Development and Cohesion Fund | 5285305.06 |
Payments monitored
€ 5,149,609.83
of which cohesion funds
€ 5,149,609.83
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2004 | 3661.30 | 3661.30 | 0 |
2005 | 208554.99 | 212216.29 | 4 |
2006 | 826236.66 | 1038452.95 | 19 |
2007 | 1391626.02 | 2430078.97 | 45 |
2008 | 1423321.44 | 3853400.41 | 72 |
2009 | 550999.00 | 4404399.41 | 83 |
2010 | 738373.13 | 5142772.54 | 97 |
2011 | 74.99 | 5142847.53 | 97 |
2012 | 6762.30 | 5149609.83 | 97 |
State of progress
Completed
Expected start: 25/07/2005
Effective start: 25/07/2005
Expected end: 03/12/2009
Effective end: 03/12/2009
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- ACQUEDOTTO LUCANO SPA
- Beneficiary
- REGIONE BASILICATA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE BASILICATA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche