CUP: G93I05000020001
FILIANO - COMPLETAMENTO AREA INDUSTRIALE DI ISCA LONGA
SUMMARY OF THE PROJECT
FILIANO - COMPLETAMENTO AREA INDUSTRIALE DI ISCA LONGA
Implementation indicator
Superficie oggetto di intervento
- Target
- 170,000 mq
- Achieved
- 170,000 mq
Funding monitored
€ 1,450,893.75
of which cohesion funds
€ 1,450,893.75
Given name | Amount |
---|---|
Development and Cohesion Fund | 1450893.75 |
- Economies:
- € 49,106.25
Payments monitored
€ 1,450,893.75
of which cohesion funds
€ 1,450,893.75
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2007 | 99901.17 | 99901.17 | 6 |
2008 | 336765.96 | 436667.13 | 30 |
2009 | 167741.48 | 604408.61 | 41 |
2010 | 261510.22 | 865918.83 | 59 |
2011 | 0 | 865918.83 | 59 |
2012 | 0 | 865918.83 | 59 |
2013 | 0 | 865918.83 | 59 |
2014 | 169115.38 | 1035034.21 | 71 |
2015 | 0 | 1035034.21 | 71 |
2016 | 199656.13 | 1234690.34 | 85 |
2017 | 0 | 1234690.34 | 85 |
2018 | 112187.55 | 1346877.89 | 92 |
2019 | 0 | 1346877.89 | 92 |
2020 | 104015.86 | 1450893.75 | 100 |
State of progress
Completed
Expected start: 20/09/2007
Effective start: 20/09/2007
Expected end: 31/07/2020
Effective end: 02/07/2020
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- COMUNE DI FILIANO
- Beneficiary
-
REGIONE BASILICATA
COMUNE DI FILIANO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE BASILICATA
- Policy Area
- Competitivita' Imprese
- Sector of intervention
- Industria e servizi