CUP: F89H10001930003
SISTEMAZIONE IDROGEOLOGICA DI ALVEI TORRENTIZI ED OPERE IDRAULICHE SUI VERSANTI DI MONTE FAITO NEL COMUNE DI CASTELLAMMARE DI STABIA (NA) INCOMBENTI SULLA VIA PANORAMICA SORRENTINA.
SUMMARY OF THE PROJECT
SISTEMAZIONE IDROGEOLOGICA DI ALVEI TORRENTIZI ED OPERE IDRAULICHE SUI VERSANTI DI MONTE FAITO NEL COMUNE DI CASTELLAMMARE DI STABIA (NA) INCOMBENTI SULLA VIA PANORAMICA SORRENTINA.
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Funding monitored
€ 10,000,000.00
of which cohesion funds
€ 10,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 10000000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 14/01/2023
Effective start: not available
Expected end: 29/02/2024
Effective end: not available
Entities
- Planning body
- REGIONE CAMPANIA
- Implementing body
- REGIONE CAMPANIA
- Beneficiary
- REGIONE CAMPANIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC CAMPANIA
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico