CUP: C91B17000310001
COMPLETAMENTO DEL MUSEO FELLINI
SUMMARY OF THE PROJECT
COMPLETAMENTO DEL MUSEO FELLINI
Funding monitored
€ 2,910,069.37
of which cohesion funds
€ 2,910,069.37
Given name | Amount |
---|---|
Development and Cohesion Fund | 2910069.37 |
- Economies:
- € 89,930.63
Payments monitored
€ 2,910,069.37
of which cohesion funds
€ 2,910,069.37
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 7676.24 | 7676.24 | 0 |
2019 | 335342.04 | 343018.28 | 11 |
2020 | 786676.08 | 1129694.36 | 38 |
2021 | 1616719.70 | 2746414.06 | 94 |
2022 | 144866.52 | 2891280.58 | 99 |
2023 | 18788.79 | 2910069.37 | 100 |
State of progress
Completed
Expected start: 25/01/2019
Effective start: 25/01/2019
Expected end: 28/02/2021
Effective end: 23/03/2022
Entities
- Planning body
- COMUNE DI RIMINI
- Implementing body
- COMUNE DI RIMINI
- Beneficiary
- COMUNE DI RIMINI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO CULTURA
- Policy Area
- Cultura
- Sector of intervention
- Patrimonio e paesaggio