CUP: B55H18004490006
LAVORI DI SISTEMAZIONE DELLA PISTA CICLABILE DEL VELODROMO OPPIDO LUCANO - DGR 1225/17
SUMMARY OF THE PROJECT
LAVORI DI SISTEMAZIONE DELLA PISTA CICLABILE DEL VELODROMO OPPIDO LUCANO - DGR 1225/17
Implementation indicator
Superficie oggetto di intervento
- Target
- 2,555 mq
- Achieved
- 2,555 mq
Download project
Funding monitored
€ 38,557.53
of which cohesion funds
€ 38,557.53
Given name | Amount |
---|---|
Development and Cohesion Fund | 38557.53 |
- Economies:
- € 1,442.47
Payments monitored
€ 38,557.53
of which cohesion funds
€ 38,557.53
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 38557.53 | 38557.53 | 100 |
State of progress
Completed
Expected start: 10/09/2018
Effective start: 10/09/2018
Expected end: 29/12/2018
Effective end: 27/12/2018
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- COMUNE DI OPPIDO LUCANO
- Beneficiary
- COMUNE DI OPPIDO LUCANO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE BASILICATA
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici