CUP: C26C19000060004
RISTRUTTURAZIONE ADEGUAMENTO ANTISISMICO E NORMATIVO, EFFICIENTAMENTO ENERGETICO DELLA SCUOLA PRIMARIA PASCOLI
SUMMARY OF THE PROJECT
RISTRUTTURAZIONE ADEGUAMENTO ANTISISMICO E NORMATIVO, EFFICIENTAMENTO ENERGETICO DELLA SCUOLA PRIMARIA PASCOLI
Implementation indicator
Superficie oggetto di intervento
- Target
- 3,696 mq
- Achieved
- 3,696 mq
Download project
Funding monitored
€ 3,257,371.04
of which cohesion funds
€ 3,200,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 3200000.00 |
Municipality | 57371.04 |
Payments monitored
€ 2,253,114.79
of which cohesion funds
€ 2,213,431.40
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 1229442.21 | 1229442.21 | 37 |
2023 | 1023672.58 | 2253114.79 | 69 |
State of progress
Open
Expected start: 28/06/2021
Effective start: 28/06/2021
Expected end: 08/08/2024
Effective end: 08/08/2024
Entities
- Planning body
- REGIONE AUTONOMA FRIULI-VENEZIA GIULIA
- Implementing body
- COMUNE DI UDINE
- Beneficiary
- COMUNE DI UDINE
Programming area
- 2021-2027 National Development and Cohesion Fund
- 2021-2027 National Development and Cohesion Fund
- Programme
- FSC ANTICIPAZIONI FRIULI-VENEZIA GIULIA 2021-2027
- Policy Area
- Istruzione e Formazione
- Sector of intervention
- Strutture educative e formative