CUP: G51B14000320002
POTENZIAMENTO DELL'IMPIANTO DI TRATTAMENTO DI ORZINUOVI - LAME (2 STRALCIO)
This project is eliminated from views and totals because its fundings are no more intended for Cohesion Policy.
Funding monitored
€ 191,839.55
of which cohesion funds
€ 0.00
Given name | Amount |
---|---|
Status: other measures | 171429.87 |
Another public source | 20409.68 |
- Economies:
- € 53,610.89
Payments monitored
€ 191,839.55
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 169109.59 | 169109.59 | 88 |
2015 | 22729.96 | 191839.55 | 100 |
State of progress
Completed
Expected start: 29/08/2014
Effective start: 29/08/2014
Expected end: 31/12/2014
Effective end: 24/12/2014
Type
- Infrastructure
- AMPLIAMENTO O POTENZIAMENTO
Theme
- Environment
- Altre misure per tutelare l'ambiente e prevenire i rischi
Territory
Entities
- Planning body
- UFFICIO DI AMBITO DI BRESCIA
- Implementing body
- A2A SPA
- Beneficiary
- A2A SPA
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
- Specific objective QSN
- Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali
Programming area
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Programme
- PIANO STRAORDINARIO TUTELA E GESTIONE RISORSA IDRICA REGIONE LOMBARDIA
- Line
- Potenziamento della capacita di depurazione dei reflui urbani
- Action
- Adeguamento impianti depurazione