CUP: B41B09000070002
COLLEGAMENTO FROSOLONE - SVINCOLO MADONNA DELLE PIANE - VARIANTE ESTERNA ALL'ABITATO DI FROSOLONE VARIANTE PARZIALE ALLA EX S.S. 618
SUMMARY OF THE PROJECT
COLLEGAMENTO FROSOLONE - SVINCOLO MADONNA DELLE PIANE - VARIANTE ESTERNA ALL'ABITATO DI FROSOLONE VARIANTE PARZIALE ALLA EX S.S. 618
Implementation indicator
Non richesto (Migrazione PSC)
- Target
- 0.01 num
- Achieved
- 0.01 num
Funding monitored
€ 5,000,000.00
of which cohesion funds
€ 5,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 5000000.00 |
Payments monitored
€ 4,438,640.19
of which cohesion funds
€ 4,438,640.19
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2004 | 8874.82 | 8874.82 | 0 |
2005 | 8874.77 | 17749.59 | 0 |
2006 | 960.00 | 18709.59 | 0 |
2007 | 2620.10 | 21329.69 | 0 |
2008 | 0 | 21329.69 | 0 |
2009 | 1630.00 | 22959.69 | 0 |
2010 | 2677.32 | 25637.01 | 0 |
2011 | 0 | 25637.01 | 0 |
2012 | 974805.47 | 1000442.48 | 20 |
2013 | 1434094.62 | 2434537.10 | 48 |
2014 | 1626681.69 | 4061218.79 | 81 |
2015 | 0 | 4061218.79 | 81 |
2016 | 0 | 4061218.79 | 81 |
2017 | 377421.40 | 4438640.19 | 88 |
State of progress
Open
Expected start: 05/11/2012
Effective start: 05/11/2012
Expected end: 30/11/2023
Effective end: not available
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI FROSOLONE
- Beneficiary
- REGIONE MOLISE
- Executor
- PQ EDILIZIA E STRADE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE MOLISE
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale