CUP: E13F11000180002
LAVORI DI RICOSTRUZIONE IMMOBILI PRIVATI IN CLASSE DI PRIORIT 'A' - PEU 44 SP 1
SUMMARY OF THE PROJECT
LAVORI DI RICOSTRUZIONE IMMOBILI PRIVATI IN CLASSE DI PRIORIT 'A' - PEU 44 SP 1
Implementation indicator
Volume oggetto di intervento
- Target
- 6,656.20 mc
- Achieved
- 6,656.20 mc
Funding monitored
€ 707,649.75
of which cohesion funds
€ 707,649.75
Given name | Amount |
---|---|
Development and Cohesion Fund | 707649.75 |
- Economies:
- € 80,252.50
Payments monitored
€ 707,649.75
of which cohesion funds
€ 707,649.75
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 136310.64 | 136310.64 | 19 |
2015 | 323188.78 | 459499.42 | 64 |
2016 | 0 | 459499.42 | 64 |
2017 | 0 | 459499.42 | 64 |
2018 | 248150.33 | 707649.75 | 100 |
State of progress
Completed
Expected start: 29/12/2011
Effective start: 29/12/2011
Expected end: 09/10/2017
Effective end: 09/10/2017
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI RIPABOTTONI
- Beneficiary
- CONSORZIO PEU 44 (COMUNE DI RIPABOTTONI)
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE MOLISE
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico